04 / Customer Economics & Cash

Your Customer Is Using Your Balance Sheet

A profitable contract can ask the seller to fund inventory, payroll and acceptance risk for months. Put a price and a limit on that funding separately.

The example below is illustrative.

Identify who funds the gap

A $900,000 project appears healthy at the bid meeting. Its incremental cash costs total $630,000 and its contribution before funding and risk is $270,000. The first supplier payment is due at kickoff. The customer pays the final balance only after its own acceptance process, which can take another month. The sales team has traded a deposit for a quicker signature. Treasury now needs to know what it was asked to provide.

Start the clock when cash first leaves. Record actual expected payment dates for materials, contractors, wages and other genuinely incremental outlays. Put deposits and customer receipts on the same calendar. Invoice dates are evidence, not cash receipts. Accepting the invoice may depend on an approval the seller cannot obtain by itself. Show that condition alongside the expected date.

Put dollars and days together

DayOutlay or receiptCumulative net cash funded
0$240,000 out$240,000
30$180,000 out$420,000
60$210,000 out$630,000
90$300,000 in$330,000
150$600,000 in$0 funded, $270,000 cumulative surplus

Peak funding is $630,000. Average funding across the first 150 days is $390,000. The peak determines whether the project fits within available liquidity. The time-weighted balance determines modeled carry. The amount funded across intervals is $58.5 million dollar-days: $240,000 × 30, $420,000 × 30, $630,000 × 30 and $330,000 × 60. At a flat 10% annual marginal borrowing cost over a 365-day year, this implies about $16,027 of carry before fees. The metric is cash funded over time. It does not value customer default or the unbilled part of a contract that could be disputed.

If the final payment moves from day 150 to day 180, the peak remains the same in this schedule and the additional carry is about $2,712. The company also stays exposed another month. If it draws $630,000 near a liquidity limit, the consequence of the peak can matter more than the interest rate. A cancellation right or a disputed acceptance milestone must be a separate downside case with recovery and resale assumptions made explicit.

A comparable diligence distinction is whether earnings can be replicated under changed operating conditions. See “Diligence verified the earnings. Not their transferability.”. The same reasoning calls for testing whether the funding and terms behind this contract are available again.

Compare terms on equivalent economics

Suppose the buyer accepts a $150,000 deposit on day 0, deducted from the day-150 balance. Peak funding falls to $480,000 and the first four intervals are each financed by $150,000 less. The funding curve falls by $22.5 million dollar-days, saving about $6,164 at the stated rate and reducing peak exposure by $150,000. Compare both benefits with any price concession requested for the deposit. A $10,000 concession exceeds the modeled interest saving alone. It could still be rational if reducing peak exposure makes other feasible work possible or substantially reduces downside. Document that reason independently.

The best term may depend on which party can verify a milestone. A deposit protects early commitments. A milestone receipt can match a major procurement outlay. A faster payment term helps after invoices are accepted. Better collections cannot retrieve time spent assembling evidence before the invoice exists. See the cash delay before invoices for that mechanism.

Translate cost into the quote using consistent denominators. The $16,027 modeled carry is about 1.8% of the $900,000 contract price and about 5.9% of its $270,000 contribution. If finance already includes a funding charge in the job, reconcile it before calculating the deduction. If borrowed dollars have a tiered cost, apply each rate only to the interval and amount for which it applies. Show any fee for holding unused credit separately. That lets the approver distinguish the price of funded exposure from the cost of ensuring liquidity is available when needed.

When longer terms are worth offering

A reliable buyer may pay a premium for extended terms, use standardized deliverables and commit enough work that cash timing is predictable. If the premium clears funding and expected credit costs on credible exposure assumptions, and the seller can carry the peak, offering terms can be a deliberate commercial product. A supplier-financed arrangement can also reduce the actual net outlay. Include its terms and concentration risk before applying a financing charge to gross expenditures.

The reverse is a strong credit name with an ambiguous acceptance process. A promise to pay within 30 days of acceptance gives limited comfort if acceptance takes three months and the supplier cannot compel a decision. Build a downside case around events each party can control. An annualized margin percentage on an order has little to say about whether the business can make payroll while it waits.

Put the schedule in front of the approver

For the next large bid, ask the controller to reconstruct cash from authorization to final collection, including plausible slower acceptance. Show contribution, peak cash funded, interest on the funding curve, contractual downside and what the customer would give up to shorten the gap. Have Treasury test the project’s peak alongside existing obligations. The growth working-capital model addresses that wider question. On signing, record which revised term paid for the risk and audit actual dates against the bid.

Take this to your team. On the week the exposure peaks, how much capital has the company committed, and what has the customer agreed to exchange for it?